California Development Critical Path · Stage 03 of 06

Submittal Clocks, Housing Streamlining, Density Bonus & CEQA Alignment

Control the Permit Streamlining Act and SB 330 submission record, synchronize CEQA project descriptions and technical studies, administer development agreements, and stack Housing Accountability Act, State Density Bonus, and <=20-acre urban infill CEQA exemptions.

5 Ordered Monographs15 Stage Q&AsGov. Code §§ 65589.5, 65905.5, 65941.1, 65943, 65950Gov. Code §§ 65915, 65913.4Pub. Res. Code §§ 21080.66 (AB 130), 21081.6, 21082.214 CCR §§ 15050, 15063, 15124, 15125

Primary Execution Gate

Are SB 330 locks, Density Bonus waivers, CEQA exemptions or studies, and contractual commitments operating from one controlled baseline?

Governing primary authorities: Gov. Code §§ 65589.5, 65905.5, 65941.1, 65943, 65950 · Gov. Code §§ 65915, 65913.4 · Pub. Res. Code §§ 21080.66 (AB 130), 21081.6, 21082.2 · 14 CCR §§ 15050, 15063, 15124, 15125

Ordered Monographs · Stage 03

Five Core Frameworks for This Stage

#11 · Entitlements & CEQA · 13 minFrom Pre-Application to Complete Application: A Submission-Control FrameworkBuild a controlled entitlement package across agency checklists, project facts, technical inputs, statutory milestones, completeness comments, and resubmittals.Control Artifact: Submission-Control Register & Completeness Matrix#12 · Entitlements & CEQA · 9 minKeeping Entitlement and CEQA Workstreams AlignedKeep the project description, technical studies, design changes, agency comments, and approval schedule aligned to one current project record.Control Artifact: 4-Record Alignment System & Assumption Crosswalk#13 · Entitlements & CEQA · 13 minControlling the Technical-Study Record: Project Assumptions, Methods, Findings, and Update TriggersControl project descriptions, baselines, methods, thresholds, assumptions, findings, inter-study dependencies, comments, and update triggers across the environmental record.Control Artifact: Technical-Study Register & Study Charter#14 · Entitlements & CEQA · 14 minDevelopment Agreements: A Lifecycle Framework for Terms, Obligations, Annual Review, and TransferTranslate negotiated terms into assigned obligations, annual-review evidence, transfer controls, amendment procedures, and a documented closeout path.Control Artifact: Development-Agreement Obligations & Annual-Review Register#15 · Entitlements & CEQA · 16 minHousing Accountability, State Density Bonus, SB 330 Vesting, and the Urban Infill CEQA ExemptionIntegrate the Housing Accountability Act (§ 65589.5), SB 330 vesting & 5-hearing cap, State Density Bonus waivers/concessions (§ 65915), SB 423 streamlining (§ 65913.4), and the AB 130 urban infill CEQA exemption (PRC § 21080.66).Control Artifact: Objective-Standards Lock, Density-Bonus & Infill Exemption Dossier

Stage Technical Reference

Related Technical Q&As (15)

What should pre-application strategy resolve?Read Sourced Answer →What does it mean for a development application to be complete?Read Sourced Answer →How are required approvals and their sequence established?Read Sourced Answer →How should agency comments and project revisions be controlled?Read Sourced Answer →How should a project team prepare for entitlement hearings and draft conditions of approval?Read Sourced Answer →How should a development agreement be managed through its lifecycle?Read Sourced Answer →How do SB 330 preliminary-application vesting, the 5-hearing cap, and Housing Accountability Act consistency clocks lock together?Read Sourced Answer →What is the operational difference between State Density Bonus concessions/incentives and development-standard waivers under Government Code section 65915?Read Sourced Answer →How are advisory, environmental-consultant, legal, and lead-agency roles divided in CEQA review?Read Sourced Answer →Who determines the applicable CEQA pathway and environmental document?Read Sourced Answer →Why does the project description require version control?Read Sourced Answer →How should technical-study assumptions and dependencies be tracked?Read Sourced Answer →What should happen when the project changes during or after CEQA review?Read Sourced Answer →How should mitigation measures and monitoring requirements move into implementation?Read Sourced Answer →When does the Public Resources Code section 21080.66 urban infill housing CEQA exemption and 30-day approval clock apply?Read Sourced Answer →