The California Development Critical Path

Every California subdivision, ministerial housing, entitlement, CEQA, post-entitlement permit, common-interest, and DRE public-report workstream organized into six sequential execution stages with explicit gate questions, paired simulators, and ordered control artifacts.

6 Lifecycle Stages30 Ordered Monographs5 Frameworks Per Stage
Parcel Fabric & Mapping

Stage 01

Acquisition, Infrastructure, Fee & Judicial-Finality Diligence

Establish what the operative approval record actually supports, test off-site access and utility rights, reconstruct fees and district burdens, place every reliance document under source control, and verify that CEQA and Map Act judicial challenge bars have closed before capital commits.

Open Stage 01 Dossier

Primary Gate Question: Does direct documentary evidence support the acquisition thesis, off-site capacity, net fee obligations, and expired judicial limitations windows?

Stage 02

Subdivision Strategy, Ministerial Maps, Vesting & Final Map Delivery

Define parcel and ownership geometry before technical mapping advances, screen 60-day ministerial 10-lot and mixed-use parcel-map pathways, preserve vesting-map reliance, govern tentative-map life across the January 1, 2027 SB 1169 transition, and sequence final-map recordation.

Open Stage 02 Dossier

Primary Gate Question: Are map pathway selection, vesting scope, operative SB 1169 expiration dates, and improvement security aligned to recordation?

Stage 03

Submittal Clocks, Housing Streamlining, Density Bonus & CEQA Alignment

Control the Permit Streamlining Act and SB 330 submission record, synchronize CEQA project descriptions and technical studies, administer development agreements, and stack Housing Accountability Act, State Density Bonus, and <=20-acre urban infill CEQA exemptions.

Open Stage 03 Dossier

Primary Gate Question: Are SB 330 locks, Density Bonus waivers, CEQA exemptions or studies, and contractual commitments operating from one controlled baseline?

Stage 04

Conditions Closure, Change Control, Permit Shot Clocks & Community Structure

Convert adopted conditions and MMRP measures into closure records, evaluate post-approval revisions under PRC § 21166, enforce 15/30/60-business-day post-entitlement building-permit shot clocks and § 66007 fee deferrals, and lock multi-association CID structure.

Open Stage 04 Dossier

Primary Gate Question: Have post-approval conditions, design refinements, post-entitlement permit shot clocks, and shared-facility duties been reconciled?

Stage 05

Association Budgets, Phase Releases, RE 648 Crosswalk & DRE Filing Readiness

Build source-supported HOA operating and reserve records, sequence multi-phase annexations and completion security, verify pre-filing DRE readiness, track live public-report dependencies, and harmonize Title 10 CCR (RE 648 / RE 616 MMDs) with Davis-Stirling mandates.

Open Stage 05 Dossier

Primary Gate Question: Do physical inventories, assessment allocations, phase boundaries, RE 648 dual-plane governing documents, and RE 624 exhibits reconcile before DRE submission?

Stage 06

DRE Comment Control, Sales Readiness, Association Turnover & Title 7 Risk

Coordinate multi-party DRE deficiency responses, classify material offering changes under 10 CCR § 2800, verify reservation-to-closing sales authority, execute developer-to-HOA turnover, and govern Title 7 (SB 800), Calderon, and § 5551 balcony-inspection records.

Open Stage 06 Dossier

Primary Gate Question: Does live offering authority match contracts, escrow instructions, turnover receipts, Title 7 maintenance manuals, and § 5551 waterproofing archives?